Safety & Capacity · Pan-India

Indian Railways ROB/RUB Programme

Ongoing SOURCE VERIFIEDSource date: 2026-08-12

Route / geography

Level-crossing replacement works across Indian Railways

Project position

Road over/under bridges replacing level crossings to improve safety and road-rail mobility.

Current public status

PIB reported 4,993 ROB/RUB works sanctioned at an approximate aggregate cost of ₹1,17,492 crore as of 1 June 2026.

Key facts

4,993 works

Approx. ₹1,17,492 crore aggregate sanctioned cost

Continuous prioritisation based on safety, mobility and feasibility